Thermal Power Station
Project Scope
H&MV carried out preventative maintenance on a 70MW EFW facility in Runcorn UK.
The maintenance included full transformer diagnostic testing on 2 No. 45MW step up transformers and 4 no. 8 MW station services transformers. H&MV provided a SAP to carry out all operational switching during the works.
The maintenance included full transformer diagnostic testing on 2 No. 45MW step up transformers and 4 no. 8 MW station services transformers. H&MV provided a SAP to carry out all operational switching during the works.
Scope of Testing & Maintenance
- Transformer Condition Analysis
- HV Switchgear Preventive Maintenance
- Oil Sample Analysis
- Thermal Imaging & PD
- Senior Authorised Personnel
Location
UK
Voltage
33/6.6 kV
Start Date
March 2015
Completion Date
March 2017
Type of Equipment
- 33 kV HV Primary Switchgear
- 4 No. 33/6.6 kV 8MVA Transformers
- 2 No. 11/33 kV 45MVA Generator Transformers
- 66 kV Primary & Secondary Switchgear
- 40 No. 6.6 kV/423v Resin Transformers
- 6 Auxiliary Voltage Systems