Ferrybridge Station

Project Scope

Hitachi Zosen Inova (HZI) required a 70 MW Biomass grid connection at 132 kV.  This was a brownfield site, therefore interface management was required.

Funding deadlines dictated tight project timelines and the project was completed on time to NPG’s design standards and functional specifications.

Location

United Kingdom

Voltage

132 kV

R

Completion Date

2018

Project Description

  • Detailed electrical engineering design & procurement, including of health and safety management

Technical Information

  • Design, supply, installation, termination and commission of the 132kV power cable.
  • Design, supply, install & commission all protection panels and relays at NPG Substation and 98 MVA power transformer.
  • Supply & installation of check 132 kV metering and generator circuit breaker.
  • Supply & installation of 11 kV IP duct/cable Interface.
    Discrimination and short circuit study, and the commissioning of a customer transformer bay.
  • Completion of G59 Interface and commissioning.